2) Cooling Tower of Ghadir Petrochemical Company, Bandar Imam
Engineering (Local), Procurement and Construction works (upto Commissioning) |
 |
| * Owner: Ghadir Petrochemical Company (Through KAR-O-ANDISHE Eng. Co., one of the HAMGAMAN'S founders)
* Inspection: Bina Consulting Engineers
* Scope of Work:
- Completion of detailed designs (by local engineering firms, especially for steel structure , concrete basin , piping , electrical and finishing activities , as well as control & instrument system) ,
- Provision of all required materials, including locally provided equipment and items,
- Construction Management (including selection and inspection on local contractors),
- Precommissioning and Start up of completed tower. |
*Start: Spring 2005
* Finish: Winter 2007 |
 |
B- In Progress:
All Construction works of Gollestan Petrochemical Complex, Gorgan(Agh-ghalla).
* Owner: Gollestan Petrochemical Industries Company.
* Inspection: Namvaran Sanat Company (As MC)
* EPC Contractor: Hampa Eng. Corporation
* Scope of work:
Construction (including all civil and earth works), Precommissioning and provision of all required services for Commissioning of a Petrochemical Plant , designed to produce Urea & Ammonia.
* Start: Spring 2008
* Contractual Execution Time:48 months
|